Schedule — planned vs actual
T-010SubstructureDonePlanned 100% · Done 100%
Planned dates: 14 Mar 2025 → 30 Nov 2025·Jum. II 09, 1447 AH
T-020Superstructure, levels 1–12In progressPlanned 80% · Done 63%
Planned dates: 01 Oct 2025 → 20 Dec 2026·Raj. 11, 1448 AH
T-030Facade installationIn progressPlanned 60% · Done 35%
Planned dates: 01 Apr 2026 → 15 Jan 2027·Sha. 07, 1448 AH
T-040MEP fit-outBlockedPlanned 46% · Done 24%
Planned dates: 01 Jun 2026 → 01 Feb 2027·Sha. 24, 1448 AH
M-001Handover milestoneNot startedPlanned 0% · Done 0%
Planned dates: 28 Feb 2027 → 28 Feb 2027·Ram. 21, 1448 AH