Site progress entries
Superstructure, levels 1–12
Level 9 slab pour completed, 2 trucks rejected on slump
By: Faisal Al-Harbi · 21 Sept 2026 · Rab. II 10, 1448 AH
160 m³
Facade installation
Glazing units installed on east elevation
By: Omar Siddiqui · 20 Sept 2026 · Rab. II 09, 1448 AH
180 m²
ApprovedMEP fit-out
Duct risers halted — shaft openings not ready
By: Faisal Al-Harbi · 19 Sept 2026 · Rab. II 08, 1448 AH
90 m