Nakheel Build ERP
Phase 1–2 Operations · Demo data
Budget SAR
SAR 37,407,400
Committed
SAR 25,772,300
Actual
SAR 14,677,900
Forecast at Completion
SAR 33,185,160
02SubstructureSAR 4,973,000
CodeDescriptionUnitPlanned QtyRateBudget SARCommittedActualDoneVariance
02-03Bulk excavation and rock cutting38,000953,610,0003,688,0003,688,000
100%
+78,000
02-08Raft foundation waterproofing9,4001451,363,00000
97%
−1,363,000
04SuperstructureSAR 7,469,200
CodeDescriptionUnitPlanned QtyRateBudget SARCommittedActualDoneVariance
04-11Concrete C40, pumped8,6004103,526,0002,168,9002,168,900
62%
−1,357,100
23-04Rebar supply & fixing, B500Bton1,2403,1803,943,2002,705,4002,705,400
65%
−1,237,800
07Envelope & FinishesSAR 12,099,200
CodeDescriptionUnitPlanned QtyRateBudget SARCommittedActualDoneVariance
07-02Facade glazing, insulated units5,2001,6408,528,0004,300,0003,017,600
35%
−4,228,000
09-15Lobby marble finishes1,2402,8803,571,20000
21%
−3,571,200
12MEPSAR 12,866,000
CodeDescriptionUnitPlanned QtyRateBudget SARCommittedActualDoneVariance
12-09MEP rough-in, levels 3–8lot111,900,00011,900,00011,900,0002,856,000
24%
0
12-22HVAC ductwork, galvanizedm4,600210966,0001,010,000242,000
24%
+44,000